This week’s construction update

The Hawaiian Dredging crews continued with the installation of concrete beam and deck forms for the third floor this past week. The installation of reinforcing steel and post tensioning cables for the third-floor deck is also underway. The MIRA crews completed the installation of new sewer laterals to each of the properties along Vineyard Street this week.

Read More
This week’s construction update

The Hawaiian Dredging crews continued with the installation of concrete beam and deck forms for the third floor this past week. The HDCC and CMC crews also continued work on the second-floor concrete columns and walls. The MIRA crews continued with the installation of new sewer laterals to each of the properties along Vineyard Street.

Read More
This week’s construction update

The Hawaiian Dredging crews began installing the concrete beam and deck forms for the third floor this past week. The HDCC and CMC crews also continued work on the second-floor concrete columns and walls. The MIRA crews continued with the installation of the sewer system improvements on Vineyard Street between Church and High Street this past week. The new sewer mainline has been completed and the MIRA crews are installing new sewer laterals to each of the properties along Vineyard Street.

Read More
This week's construction update

The Hawaiian Dredging crews poured the second section of the parking structures second-floor concrete deck this week. The HDCC and CMC crews also continued work on the second floor concrete columns and walls. The MIRA crews continued with the installation of the sewer system improvements on Vineyard Street between Church and High Street this past week. The Hawaiian Electric, MIRA and Wasa Electric crews also converted the existing overhead electrical service to the Weinberg Building on Lower Vineyard Street to underground this past week.

Read More
This week’s construction update

The Hawaiian Dredging and CMC crews completed the installation of reinforcing steel and post tensioning cables for the second section of the parking structures second-floor concrete deck and will be pouring the concrete deck next week Monday starting at 4:00 am in the morning. The HDCC and CMC crews also continued work on the second-floor concrete columns and walls. The MIRA crews continued with the installation of the sewer system improvements on Vineyard Street between Church and High Street this past week.

Read More